Let p = number of cu. ft. cement paste per bbl., as determined by actual test. n = number of cu. ft. of cement per bbl., as specified in the specifications. s = parts of sand (by volume) to one part of cement, as specified. g = parts of gravel or broken stone (by volume) to one part of cement, as specified. v = percentage of voids in the dry sand, as determined by test. V = percentage of voids in the gravel or stone, as determined by test.
Then, in a mortar of 1 part cement to s parts sand, we have:
n s = cu. ft. of dry sand to 1 bbl. of cement. n s v = " " " voids in the dry sand. 0.9 n s v = " " " available voids in the wet sand. 1.1 n s = " " " wet sand. p - 0.9 n s v = " " " cement paste in excess of the voids.